Erickson RLTV
Erickson Corporation owns and operates retirement living communities throughout the United States. RLTV, retirement living television, is their new venture into television programming aimed at retirement aged people. Their new facility is a 100,000 sq. ft. five floor building located at the University of Maryland Baltimore Campus.
The building will also house Erickson Corporate Data Center. Co-locating these two functions takes advantage of the common "critical" nature of a television station and a data center. These critical systems include: redundant mechanical systems, emergency generators for full back up power, UPS systems. The design was developed with modular schemes to address the start-up nature of the owner's tv business as well as to allow for future growth of the data center. tic system and connections to city water and sewer services.
• 100,000 sq .ft. new out-of-ground construction
• Three full production studios.
• Master control room.
• Main television equipment room.
• 15,000 s.f. data center.
• Central rooftop chiller plant.
• Diesel generator.
• Central UPS.
• 40,000 s.f. office space.
• Dining facility with full commercial kitchen
• Erickson Retirement New Broadcast Facility
• Sprint Herndon 4G Lab
• Nextel Brazil MSO II review
• Verizon Dulles Building addition
• Nextel Design Standards
• Verizon Rockville Bldg Addition
• Nextel Hanover UPS installation
• Nextel Peru MSO1 Upgrade Feasibility Study
• Nextel UPS Installation Standard
• Nextel-Nashville, TN Site Expansion
• Sprint Beltsville Switch Room Expansion
• Sprint Sterling Lab ACU Replacement
• Verizon 730 12th street Cooling Tower
• Sprint Sterling Lab Expansion
• Sprint Teterboro Control Room Relocation
• Verizon 722 12th Building Sale
• Verizon Building Additions/Upgrades
• Verizon Cameron Switchboard Replacement
• Verizon Chesapeake Pod C - Cal III Consolid
• Verizon Crystal City Building addition
• Verizon Fairfax Building Addition
• Verizon Fairfax Generator
• Verizon Germantown Bldg Addition
• Verizon Hyattsville Power Upgrade
• Verizon Poolesville Bldg Addition
• Verizon Sterling Park Building Addition
• Verizon Woodley 1st Floor Switchboard
• Verizon Woodley Chiller Plant Upgrade
• Sprint Hanover Generator and service study
• Sprint Hanover Generator Load Balance
• Sprint Silver Spring Generator Load Balance
• Sprint Herndon 4G Lab
• Nextel Brazil MSO II review
• Verizon Dulles Building addition
• Nextel Design Standards
• Verizon Rockville Bldg Addition
• Nextel Hanover UPS installation
• Nextel Peru MSO1 Upgrade Feasibility Study
• Nextel UPS Installation Standard
• Nextel-Nashville, TN Site Expansion
• Sprint Beltsville Switch Room Expansion
• Sprint Sterling Lab ACU Replacement
• Verizon 730 12th street Cooling Tower
• Sprint Sterling Lab Expansion
• Sprint Teterboro Control Room Relocation
• Verizon 722 12th Building Sale
• Verizon Building Additions/Upgrades
• Verizon Cameron Switchboard Replacement
• Verizon Chesapeake Pod C - Cal III Consolid
• Verizon Crystal City Building addition
• Verizon Fairfax Building Addition
• Verizon Fairfax Generator
• Verizon Germantown Bldg Addition
• Verizon Hyattsville Power Upgrade
• Verizon Poolesville Bldg Addition
• Verizon Sterling Park Building Addition
• Verizon Woodley 1st Floor Switchboard
• Verizon Woodley Chiller Plant Upgrade
• Sprint Hanover Generator and service study
• Sprint Hanover Generator Load Balance
• Sprint Silver Spring Generator Load Balance